Work plan

When writing the proposal, we don’t need to write the detailed activities in the work plan. So we write the main activities that we wrote in the proposal itself. What we need in the work plan is to clarify the period of time to implement each main activity (in months not weeks). Therefore, we shade the months in which we expect each activity is going to be implemented as in the table below:

A model of the work plan required in the project proposal

Note: 

The Work plan of the proposal should contain answers for the following questions:

  • 1-What? What are the activities planned for implementation?
  • 2-When? The period of time in which activities are expected to be implemented.

Previous: Logframe (Activities)
Next: Targeted Groups and Final Beneficiaries

Have any questions? We'd be happy to answer them
_________________________________________

Would you like to use Portal365?

Did this answer your question?